Zuidhorn Bridge Locked Up for Months as Rijkswaterstaat Plans Shuttle Buses and a Temporary Crossing

Shipping takes precedence because the canal is a key national corridor for inland freight.

Overview

  • After inspections found multiple breaks in the steel lifting cables, the table bridge at Zuidhorn was raised and closed to all road users for safety.
  • Rijkswaterstaat has ordered new cables and expects road access to remain suspended until at least late February 2026, possibly mid-March, citing supply delays over the holiday period.
  • Two shuttle buses will operate next week, and a temporary scaffolding bridge for pedestrians and cyclists is planned shortly after New Year, expected to be about five meters high with walking required for bikes.
  • A ferry option was ruled out as too slow to arrange and unsafe given heavy barge traffic and limited winter daylight.
  • Similar cable issues were identified at Dorkwerd and Aduard, with Dorkwerd already out of service after a collision and Aduard remaining operational under close monitoring while the root cause is investigated.