Western Way Roadwork Near Walt Disney World Begins June 29, 2026

The 60-day phased project will keep lanes open while scheduled closures are expected to slow peak summer arrivals and resort staff travel.

Overview

  • The Central Florida Tourism Oversight District put a bid in place that schedules the work to start June 29, 2026 and run for 60 days, with an expected end around August 28, 2026.
  • The contract includes a full grade-separated interchange at Buena Vista Drive and Western Way that raises Buena Vista Drive over Western Way with ramps to separate traffic movements.
  • Western Way will be widened from four lanes to six across a 2.45-mile stretch running east from the SR 429/Western Way boundary toward the Coronado Springs driveway.
  • Roads will remain open during construction but phased lane closures are planned, which reporters and officials say will worsen congestion for summer visitors and on-site Cast Members.
  • Travelers approaching from SR 429 and guests at western-side resorts such as Coronado Springs should plan extra travel time, use real-time navigation, or choose Disney transit options, while the full interchange and widening aim to deliver long-term relief once completed.