Watchdog Says Most B-52 Modernization Efforts Face Cost, Schedule and Performance Problems

The GAO warns the problems could push up costs and slow upgrades in ways that harm depot work and the bomber fleet’s readiness.

Overview

  • The Government Accountability Office found that 10 of 13 B-52 upgrade efforts are experiencing cost, schedule, or performance problems and that the Air Force plans about $21 billion to modernize 76 aircraft.
  • The Commercial Engine Replacement Program has grown by roughly $3 billion and suffered more than a 15-month capability delay after the Air Force began production with minimal developmental flight testing.
  • The Radar Modernization Program has also seen major cost increases and schedule slips, and June’s test-aircraft crash paused some radar flight testing while the Air Force moves work to a second modified B-52 to keep development moving.
  • GAO issued six recommendations, including pausing CERP production until risks are analyzed, updating sustainment timelines, and expanding digital engineering; the Air Force agreed with most recommendations but only partially agreed to delay CERP production.
  • If engine replacements slip, current depot plans that move B-52s through maintenance every four years may not be viable, risking spare-part shortages, heavier workloads for maintainers, and fewer mission-capable bombers for operations.