Overview
- Construction has started in Huasao, a town in Oropesa, Quispicanchi, with Universidad Andina as the project promoter.
- The initial outlay tops S/4 million, funding early works that set up the field and basic services.
- The first phase runs about 180 days and installs drainage, automated irrigation, restrooms, and locker rooms.
- The second phase adds the first ring of stands for more than 23,000 fans plus underground parking, medical areas, and a high-performance center.
- The third phase lifts capacity by roughly 13,000 more seats and adds a roof, VIP boxes, and broadcast booths, with full completion projected in about four years.