UConn Begins $99.4 Million Gampel Pavilion Renovation

The bond-funded overhaul signals a push to match the program’s standards with modern facilities.

Overview

  • UConn, which began Phase 1 on Tuesday, is replacing the roof and adding new locker rooms, lounges, a recruiting lounge, sports medicine space, and a press room.
  • The $99.4 million project uses non-tax UConn 2000 bonds authorized by the General Assembly, following Board of Trustees approval in December.
  • Phase 1 is slated to finish by November 2026, with Phase 2 set for March 2027 to add premium and philanthropy-focused spaces that generate new revenue.
  • Fans will see four grab-and-go stands at each corner to cut lines that have clogged aisles and restrooms during games.
  • DPR Construction and S/L/A/M Collaborative are delivering the overhaul at the 1990 arena, which recently added giant videoboards and new lower-bowl seating.