Overview
- A cross-party group of Santa Fe lawmakers filed a resolution urging the national government to resume works and evaluate ceding jurisdiction to the province.
- Governor Maximiliano Pullaro says he will ask Interior Minister Diego Santilli for a handover so the province can finance the remaining 28% of the project.
- The contractor Dyscon reports the site is paused at roughly 72% completion because about 1.6 billion pesos in national payments are outstanding.
- Dyscon’s president says work could restart within days if the transfer and payment guarantees are formalized, estimating about two and a half months to finish.
- Unfinished areas include the Sala de las Banderas, the tower lookout and the central fountain, with missing climatization, paint and glass preventing public use.