Overview
- Dos Bocas has been out of service since Monday due to a power cut, Reuters reported citing sources, with attempts to restart expected Thursday and no official comment from Pemex.
- In July, the Olmeca facility processed 156,265 barrels per day, an 18% month‑on‑month drop that left utilization near 46% of its 340,000 bpd design; fuel output also slipped versus June.
- Across the system, Pemex refineries processed about 1.02–1.023 million bpd in July, roughly 7.5% lower than June, reflecting broader operational softness.
- Crude exports rebounded to 600,669 bpd in July, up 31% from June, while imports of refined products remained heavy at 566,102 bpd, including 345,807 bpd of gasoline.
- Pemex reported crude output of 1.379 million bpd and total liquids of 1.648 million bpd in July, extending a 32‑month streak of year‑over‑year declines as President Claudia Sheinbaum cites field depletion and targets 1.8 million bpd.