Peru Confirms Key Piura Flood Pumps Work After Emergency Drill

Authorities ordered targeted fixes within 30 to 60 days to shore up pumps, power backups and equipment protection before the November rainy season.

Overview

  • The Ministry of Housing led inspections and a full simulacro in Piura that tested crisis-room coordination, a simulated power outage and deployment of pumps, with the exercise reported on July 10.
  • Technicians found inspected SAREs generally operational, with La Molina II confirmed to hold 3,000 cubic meters and two electropumps rated at 300 liters per second.
  • Inspectors identified installation and perimeter-protection flaws such as low-mounted equipment at risk of flood damage and lack of anti-vandal fencing that must be corrected in 30 to 60 days.
  • EPS Grau committed to stepped-up preventive maintenance including hydrojet cleaning, coordinated availability of electropumps and motobombas, and purchase of generators to keep pumping stations running during outages.
  • Officials warned that Piura’s urban growth has created 'cuencas ciegas'—basins without natural outlets—that can trap water and may require drainage adaptations, and the MVCS will issue a consolidated technical report to assign repairs and responsibilities before the rains.