Overview
- NHSRCL says all foundation and substructure work on the river crossing is complete.
- Three of the five 76‑metre spans are finished, with pier head work and segment casting in progress.
- All eight circular piers are in place, with four in the riverbed, two on the banks, and two outside the banks.
- Crews use the balanced cantilever method, which builds each span from 23 cast‑in‑place segments without scaffolding under the deck.
- Temporary culverts in an embankment and a kept discharge channel maintain continuous water flow during construction.