Overview
- Initial construction will run at Bollinger Shipyards and Fincantieri Marinette Marine, with Fincantieri slated to build four ships.
- The VCM will hold the prime contract, issue and manage subcontracts, and exert direct contractual control to reduce cost and schedule risk.
- The Navy expects to award the VCM contract in mid-2026, with the manager empowered to allocate the remaining three ships under the base award.
- Damen Naval’s LST-100 is the selected non-developmental baseline, enabling a faster, build-to-print start for the class.
- The FY2026 NDAA authorizes use of the VCM for the first eight LSMs, as the program targets a 35-ship fleet to support Marine littoral mobility and distributed logistics.