MumbaiPune Expressway Enforces 3-Hour Blocks for Bridge Work on April 23–24

The daytime blocks clear the way for last-stage bridge work linked to a new bypass expected to cut trips by up to 30 minutes.

Overview

  • MSRDC halted Mumbai-bound traffic from 12 pm to 3 pm Thursday near km 58/500 to remove shuttering and paint a bridge.
  • Vehicles to Mumbai were routed via Kiwale–Dehu RoadTalegaon onto NH-48 and rejoined at the Kusgaon toll plaza.
  • Pune-bound traffic will be fully blocked from 12 pm to 3 pm Friday, with diversions from Kusgaon via NH-48 through Dehu Road and Kiwale.
  • Following Wednesday's heavy build-up near Lonavala, reports showed a roughly 5 km jam as lane closures and bridge load tests for the Missing Link slowed traffic.
  • Officials say the 13.3 km Missing Link is slated to finish by April 25 and open May 1, and they posted help lines for drivers at 9822498224 and 9833498334.