Overview
- Traffic returned to normal Friday on the left express lane of Avenida Morones Prieto following a six‑day closure tied to Line 4 construction work.
- Municipal authorities formalized the damage in a supervision act attended by city officials, state mobility representatives, and the construction firm Magna.
- City inspectors previously halted an attempted reopening that lacked full reconstruction, specifying the need for excavation, layered compaction, and asphalt replacement.
- Inspections recorded cracks up to three centimeters that formed without vehicle load, indicating an unstable base and risk of further subsidence.
- Mayor Adrián de la Garza said the fix should have taken two days, as the state pressed to restore circulation, while local commentary cast the episode as a political clash.