Overview
- Modi, who will join virtually from Hyderabad on May 10, will open the Kakatiya Mega Textile Park in Warangal.
- The park spans 1,327 acres as a brownfield site under the PM MITRA scheme, with about 62% of space allotted to anchor investors.
- The government pegs project cost at ₹1,695.54 crore and expects over ₹6,000 crore in total investment, with more than ₹3,800 crore already grounded.
- Internal roads, water lines and street lights are complete, a 12 MLD water system is in advanced stages, a 5 MLD effluent plant with zero liquid discharge is on trial, and the substation with a 220 kV line is nearing completion.
- Officials say around 2,000 jobs have begun at the site and more than 24,400 roles are projected as the hub advances the ‘5F’ pipeline from farms to exports through plug-and-play factory space.