Overview
- The staged relocation took place on Tuesday and continued on Wednesday with departments operating from the new building while the hospital moved patients and equipment.
- Emergency dispatch temporarily deregistered the children's emergency department on both days and the adult emergency department on Wednesday, so ambulances were directed to other hospitals.
- About 300 patients were moved during the two days, many transported lying in their beds, and staff used simulation training to keep urgent procedures such as emergency cesareans possible during the move.
- Logistics included distributing roughly 3,500 packing boxes, transferring large diagnostic devices with specialist firms, and shifting about 340 doctors plus 870 nursing and support staff to new workflows in the Neubau.
- The €255 million Neubau brings multiple high‑acuity specialties into one site and the clinic says full clinical services will resume on Thursday, June 11, with updated phone numbers and guidance posted online.