Meta to Build $1.5 Billion AI Data Center in El Paso

The project signals the Borderland's emergence as an AI data center hub, featuring firm timelines, defined job totals, renewable matching commitments, water restoration plans.

Overview

  • The El Paso campus is designed to scale to 1 gigawatt of capacity and is targeted to begin operations in 2028.
  • Meta projects roughly 1,800 peak construction roles and about 100 permanent jobs at the facility.
  • The company says it will match electricity use with 100% renewable energy, deploy closed-loop liquid cooling, and restore 200% of the water consumed to local watersheds.
  • Meta is funding new transmission lines and substations through its agreement with El Paso Electric, while El Paso previously approved incentives including an 80% city property-tax rebate per phase over 25 years.
  • The site becomes Meta’s 29th data center and third in Texas, reinforcing a Borderland buildout that includes OpenAI and Oracle projects in nearby Santa Teresa.