Maryland Resets Key Bridge Rebuild After Kiewit Split and Sets New 2030 Target

The state is breaking the work into four separate contracts to try to lower costs and reassure federal lawmakers who agreed to fund the project.

Overview

  • State leaders led a bipartisan boat tour on Monday to show ongoing marine site work and explain a procurement reset after cancelling Kiewit’s Phase 2 bid.
  • Officials say Kiewit will finish Phase 1 site work through at least the end of this year while Maryland seeks new contractors for later phases.
  • Estimated costs have risen from roughly $1.8–$1.9 billion to about $4.3 billion to $5.2 billion, and the state confirms the rebuild target is now around 2030.
  • Engineers are driving large foundation piles now, with about 80 eight-foot piles installed so far, and the new design calls for roughly 600-foot pylons and about 230 feet of deck clearance.
  • Congress in late 2024 approved a full federal pay‑up for the replacement, a rare 100% cost-share that has kept federal oversight and appropriators closely involved as the state pursues the four-contract strategy.