Overview
- Council papers put the investment at just under £4 million, with a Cabinet decision scheduled for the week of 24 February.
- The scheme will deliver resurfaced carriageways, wider footways, upgraded crossings, new bus shelters, tactile paving and a reduced 20mph speed limit.
- Designs were developed with Merseytravel, Liverpool FC, emergency services and local residents following consultation.
- Construction is slated to start in May and run about seven months, with completion anticipated toward year-end.
- Parking arrangements and matchday traffic flows will be reviewed during the works as part of the transport plan.