Particle.news
Download on the App Store

Kolkata Metro Finishes Girder Work at Chingrighata

Completion removes a critical bottleneck, allowing engineers to begin track-laying, signalling work followed by trials toward a December 2026 Sector V target.

Overview

  • Kolkata Metro and RVNL completed girder-launching at Chingrighata in the early hours of Monday, May 25, 2026, and normal traffic on the EM Bypass was restored ahead of schedule.
  • Engineers used two consecutive weekend night traffic blocks to place all segments between piers 317–319, finishing chemical pasting and most traction cabling with only curing remaining.
  • With the viaduct gap closed, Metro Railway and RVNL plan immediate track-laying, signalling cable installation and phased trials before seeking statutory clearance from the commissioner of railway safety.
  • Officials say the work removes the biggest bottleneck on the New Garia–Airport Orange Line and they are targeting commercial service to Sector V by December 2026 and the airport extension by late 2027 or early 2028.
  • The project was stalled for roughly 18–24 months by refusals to grant traffic-block permissions, a delay that prompted directions from the Calcutta High Court and the Supreme Court; other viaduct gaps at VIP Road and near Technopolis still need permissions and work.