Overview
- Officials said hydropower reached about 4,950 to 5,125 megawatts during recent peak hours, and an extra 400 megawatts flowed from the south, yet utilities still imposed roughly two to two-and-a-half hours of evening load management.
- About 5,500 megawatts of LNG-based generation remains offline due to a lack of fuel, and the Power Division says peak-time cuts should end once LNG deliveries restart in early May.
- Lahore Electric Supply Company reported an evening demand of 3,787 megawatts against 3,053 megawatts of supply, a 682 megawatt gap that led to two-hour curbs on commercial and industry-heavy feeders while uninterrupted power continued for independent industry.
- Residents in parts of Punjab continue to report far longer and unannounced outages than officials describe, with some rural areas earlier citing 12 to 16 hours without power, highlighting a sharp gap between policy and lived experience.
- The government defends revenue-based load shedding on high-loss feeders to deter theft and limit financial losses, but the regulator NEPRA and the Law Ministry have called the practice illegal, setting up a policy and legal clash that could shape how cuts are assigned.