Haverhill Sewer Breaks Dump Millions of Gallons Into Merrimack River

State and city crews are racing to install temporary bypass pipes to stop the discharge so beaches and shellfish areas can be reopened if water tests clear.

Overview

  • A 42-inch pressurized sewer force main at Haverhill’s South Mill Street pump station ruptured during Friday’s heavy storm and crews found a second break while inspecting the line.
  • City officials estimate about 8 to 10 million gallons of untreated wastewater have been entering the Merrimack River each day since the failures.
  • Contractors are working around the clock to fuse and place temporary bypass pipelines that officials say should reduce or halt the river discharge within 24 to 72 hours pending installation.
  • Multiple North Shore beaches have been closed to swimming and several shellfish growing areas are under precautionary closure while state agencies run bacterial and pollutant tests to set reopening dates.
  • Officials say drinking water is unaffected, state leaders have opened a coordinated response and investigation, and short‑term bypass work is expected to cost millions with full repairs likely far higher because the system dates to the 1970s.