Haunted Mansion Scrims Come Down to Reveal Restored 1971 Facade

The reveal shows a high-contrast, opening-day color scheme and follows months of preservation work that also prepares sightlines for the nearby Piston Peak expansion.

Overview

  • Scrims began coming down on Thursday, July 23, 2026, exposing the Haunted Mansion’s refreshed exterior after months of scaffolding and tarps that covered the attraction earlier this year.
  • Visible changes include a patina green cupola, noticeably darker red-brown brickwork, and much lighter stone trim that together recreate the ride’s original 1971 palette.
  • Reporters say crews performed preservation work behind the tarps such as masonry repointing, conservatory resealing, and roof shingle replacement rather than only repainting the facade.
  • The interactive graveyard queue has been altered with some tombstones moved and a nearby exit wall shows unfinished whitewashing, changes that tie into guest-flow adjustments and new sightline planning for the Piston Peak Cars expansion.
  • The project stretched across the first half of 2026 because Florida’s heat, humidity, heavy rain, and UV exposure forced deeper structural repairs; the ride reportedly stayed open during the work and the restoration aims to protect the building for decades more.