Overview
- At the 33rd HRIDC Board meeting, officials said all civil, track, signalling, telecom and OHE works on the Kurukshetra Elevated Track are complete, with the platform in an advanced stage.
- The completed KET works will be offered first to Northern Railways for technical inspection, followed by review by the Commissioner of Railway Safety.
- On the Haryana Orbital Rail Corridor, the Manesar–Patli section and Maruti rail yard commissioned in June have handled 372 rakes from the Manesar plant, generating revenue.
- For the Eastern Orbital Rail Corridor from Sonipat to Palwal, a steering committee chaired by the Uttar Pradesh Chief Secretary approved the alignment for study, and the feasibility assessment is in an advanced stage.
- HRIDC reported in-principle forest clearance for HORC Stage I, submission of the Aravalli clearance application, and land-compensation disbursements of Rs 1,533 crore against Rs 1,878 crore in awards, with Rs 99 crore paid against arbitration awards, as the Chief Secretary urged the corporation to pursue a national footprint.