- Emape completed the overnight assembly at Esteban Camere in Surco, lifting three metal modules with a heavy crane over roughly five hours.
- The program calls for four temporary footbridges of about 60 meters each, with installation targeted within approximately six weeks subject to technical and weather conditions.
- After the lift, crews will add vertical and horizontal signage, paint crosswalks, and build access sidewalks to organize pedestrian flow.
- Preparatory works are underway for the next crossings at Doña Elsa, García García, and Los Vicus, including excavations and platform assembly.
- The rollout follows months of neighborhood complaints over missing crossings and media reports of a pedestrian death since the roadway opened.