Overview
- Construction officially began on the Sunrise Expansion Program on July 20, 2026, after federal approval in April and a rapid move from permitting to ground work.
- The $4-billion Enbridge project will add roughly 139–140 kilometres of pipeline looping and related upgrades to increase Westcoast system capacity by about 300 million cubic feet per day.
- The federal government and Enbridge say the build will create about 2,500 jobs during construction, generate roughly $700 million in tax revenue, and add over $3 billion to Canada’s GDP.
- The expansion builds on Indigenous participation after 38 First Nations took a 12.5% ownership stake last year and will use Canadian-made materials, including 100% Canadian-melted steel from InterPro Pipe + Steel.
- Supporters say the work will help supply domestic needs and LNG export projects such as Woodfibre LNG, while critics warn the new infrastructure could lock in fossil-fuel emissions and risk stranded assets if export demand shifts.