Controlled Blast Fells A7 Bridge Sections as Stretch Closes Until Late Afternoon

Specialists are verifying the blast outcome ahead of the next bridge segment due by late 2027.

Overview

  • Two old sections of the Talbrücke Thalaubach near the Fulda interchange were demolished in a controlled operation that Autobahn GmbH said went to plan.
  • The A7 is closed in both directions between Dreieck Fulda and the Bad Brückenau-Volkers junction until about 16:00, with signed detours for drivers.
  • Reports cite the use of roughly 100 kilograms of explosives for the demolition.
  • Traffic has been running with two lanes per direction on a new bridge segment that opened last August.
  • The wider replacement program foresees the Würzburg-bound segment finished by the end of 2027, route adjustments by 2030, and about €115 million in total costs, while increased traffic on the A49 has prompted noise checks and a possible 80 km/h limit under review.