Overview
- The Contraloría issued a field control report in mid‑June that notified INVERMET of multiple irregularities on the Próceres‑Wiesse project and asked the agency to adopt corrective measures.
- Inspectors found that work on the Paso a Desnivel No. 5 at Wiesse and El Muro began on Oct. 1, 2025 without formal Sedapal authorization to free water and sewer interferences, a required permit for such interventions.
- The same component showed just 18.93% physical progress at the end of April 2026 versus a planned 91.56%, a shortfall that makes the project’s November 2026 completion date unlikely without major recovery measures.
- Audit teams documented material and workmanship problems on site, including exposed reinforcing steel with visible rust, a pillar with superficial corrosion, and cement bags stored outdoors in poor conditions that could reduce durability.
- The Contraloría found ten engineers working on execution and supervision lacked current habilitación from the Colegio de Ingenieros, which can call into question the legal validity of signed technical documents and trigger administrative or contractual consequences.