Overview
- Commonwealth Fusion Systems, which filed Tuesday, became the first fusion developer to seek a PJM grid interconnection for its planned ARC power plant.
- The application covers a roughly 400 megawatt facility at the Fall Line Fusion Power Station site in Chesterfield County, Virginia.
- PJM, the largest U.S. grid operator serving more than 65 million people, will run detailed studies that often take four to six years and can require network upgrades before a plant can connect.
- CFS targets starting construction around 2027, says work could begin as early as late 2026, and aims to deliver electricity in the early 2030s.
- The company says it has raised nearly $3 billion, secured utility guidance from Dominion Energy, and signed offtake deals with Google and Eni as PJM manages a heavy queue and rising demand from data centers and electrification.