Overview
- Commonwealth Fusion Systems, which filed Tuesday, became the first fusion developer to seek connection to PJM, the largest U.S. grid operator.
- The company plans to plug in its 400-megawatt ARC unit at the Fall Line Fusion Power Station in Chesterfield County, Virginia.
- PJM will run interconnection studies that typically take four to six years, and the operator is working through a large backlog.
- The company outlines a path that includes a SPARC test in 2027, construction of ARC as early as late 2026, and first power in the early 2030s.
- CFS says the move builds on 2025 steps that included a local permit, power offtake deals with Google and Eni, and U.S. Energy Department validation of its magnet technology.