Overview
- Ottawa approved Enbridge’s Sunrise expansion on Friday with 47 binding conditions after a regulator panel endorsed it in late January.
- The C$4 billion project adds about 139 kilometres of looped pipe plus new compression to lift the T‑South system by up to 300 million cubic feet a day.
- Enbridge plans to begin construction in July 2026 with service targeted for late 2028.
- Government and company estimates point to more than C$3 billion added to GDP, over C$700 million in taxes, and about 2,500 construction jobs, with Indigenous groups holding a 12.5% stake in the existing line.
- The added capacity is meant to shore up B.C. gas supply and support LNG plants such as Woodfibre, while environmental advocates criticized the decision for clashing with climate goals.