Overview
- The blaze began in a billiard-table factory on Rua Sampaio Moreira and spread to nearby warehouses, destroying at least three commercial properties with no injuries reported.
- The response peaked at about 30 fire vehicles and roughly 60 personnel before shifting into the rescaldo, or overhaul, stage to cool hotspots.
- Structural damage, including a partial slab collapse, made entry unsafe so teams attacked from the street and a school parking area behind the site.
- Crews held containment with seven trucks and about 20 firefighters as of the latest update, and officials have not identified the cause.
- Enel cut power across roughly a 1 km radius to protect firefighters, and Sabesp kept water service by routing supply to the scene.