Overview
- The TCU unanimously blocked the immediate federal disbursement and barred APS from transferring money to the PPP until the court’s conditions are met.
- Relator Bruno Dantas cited a legal vacuum over the Union’s role and noted institutional resistance by São Paulo state and Artesp to giving APS a defined position.
- APS says it holds R$2.6 billion in a Banco do Brasil account and presented proof to the ports minister, asserting the decision should not delay the construction timetable.
- The court extended earlier requirements, including hiring an accredited independent inspection body and tying releases to defined project milestones for transparency.
- The tunnel is a state‑led PPP won by Mota‑Engil, with total investment near R$6.8 billion and federal participation expected to finance roughly half of the public contribution.