Overview
- The Bengaluru Central City Corporation will relay a 2.2 km stretch between Trinity Circle and Cubbon Park Police Station Circle.
- Night-time milling began on March 4 with patchwork and overnight debris clearing to keep daytime traffic flowing.
- Vehicles can use the milled surface for roughly eight to nine days, with full diversions to follow as asphalt laying proceeds.
- A proposed white-top was rejected by traffic police, and BWSSB deferred replacing 40-year-old pipelines due to the accelerated schedule.
- The project is funded under a Rs 25 crore package for seven Shantinagar roads, and a separate closure toward Bangalore University runs from 6 pm Thursday to noon Friday for railway bridge girder work with designated detours.