Bellasis Flyover Rebuilt in 15 Months, Opening Awaits Railway NOC

Final opening depends on a railway no‑objection certificate, with a staircase to reconnect the station link already under way.

Overview

  • BMC says the reconstruction of the east–west connector at Mumbai Central is complete and ready for use.
  • The project finished in 15 months and six days, roughly four months ahead of the tendered schedule.
  • Finishing works wrapped on January 6, followed by load testing, structural stability and safety certifications.
  • Traffic will be allowed after Western Railway issues an NOC and coordination is completed with the Mumbai traffic police, following a joint inspection on January 20.
  • Western Railway is constructing a staircase to restore the foot overbridge connection altered by the higher new alignment, with the reopening expected to ease congestion between Tardeo, Nagpada and Mumbai Central.