Overview
- The government published an eight‑year schedule for health construction and upgrades across Euskadi, committing €1.6 billion to Osakidetza through 2032.
- The flagship project in Gipuzkoa is a new Hospital of Tolosa with 74 beds and three surgical blocks, budgeted at €107 million with works slated to start in late 2026 and finish in 2031.
- Donostia’s Hospital Universitario will host a €61.4 million proton therapy unit expected to receive its first patient at the end of 2027 and serve surrounding provinces and regions.
- The plan adds 21 new primary‑care centers and fully renovates or expands eight more, allocating €200.8 million, with works beginning this year at Loiola‑Txomin and in 2026 at Oinaurre (Irun), Lazkao and Elgoibar.
- Further hospital projects include Donostia’s new outpatient building with €33.2 million programmed to 2032, Arrasate’s €27 million upgrade targeted for 2027, new surgical blocks at Zumarraga (€75 million, ready 2029) and Bidasoa (€24.8 million, in service in the second half of 2028).