Overview
- AVAX One signed a Front End Engineering & Design proposal with BlueFlare for a 10 megawatt AI and high-performance computing microgrid in Alberta.
- The FEED requires no upfront capital from AVAX One and will be reviewed by an independent international engineering firm before any final investment decision.
- The 4-31 Battery site uses behind-the-meter natural gas and sits near 138 kV transmission with redundant fiber and highway access, which can cut power costs and allow power export.
- To earn revenue during construction, the company bought 220 Bitmain Antminer S21 Pro rigs for under $500,000, lifting its Alberta hash rate about 33% to more than 200 PH/s.
- Management is positioning a hybrid model that pairs AI compute hosting with Bitcoin mining, which a KuCoin note says can improve risk-reward by turning idle capacity into cash flow.