Overview
- Peru’s comptroller warned the shortfall threatens continuity this year for the link between the Costa Verde and the new Jorge Chávez airport.
- The project management office told Provías Nacional current resources do not cover the physical and financial baseline or the payment plan, heightening risks of stoppages, reprogramming and contractor claims.
- Multiannual investment programming indicates the budget risk could persist through 2027–2029, according to the control report.
- Provías moved to terminate a state-to-state technical assistance deal with a firm representing France, but the effect is suspended pending direct talks until April 6, so PMO Vías continues assisting.
- The execution contract for the main works remains unsigned and uncertain, while the energy and mines minister maintains the official timetable will be met.